Q: Is Scheduling Plus a stand alone product?
A: It can be, but most builders and contractors purchase Scheduling Plus as part of our other applications because it keep them from having to re-enter information more than once.
Q: Does Scheduling Plus integrate to TakeOff Plus?
A: Yes, Scheduling Plus integrates with TakeOff Plus, Accounting Plus and SalesBuilder Plus. It will allow you to pick the bids from Take Off Plus and automatically setup the activities (and vendors attached to those activities) directly into the project schedule within Scheduling Plus.
Q: Does Scheduling Plus generate a bar chart for the schedule?
A: Yes. Scheduling Plus has the ability to create charts with or without percentages showing.
Q: How many types of task dependencies are available?
A:
Scheduling Plus presently has 4 task dependencies available, but we would be more than happy to add more to fit your needs. Scheduling Plus currently includes the following dependencies:
- Finish to Start - Current Task Code cannot start until Task 1 finishes
- Start to Start - Current Task Code cannot start until Task 1 starts
- Finish to Finish - Current Task Code cannot finish until Task 1 finishes
- Finish to Start - Current Task Code cannot finish until Task 1 starts
Q: Is it possible to view a vendor's schedule across multiple projects?
A: Yes, Scheduling Plus allows you to view all the projects for a specific vendor at one time.